PMU4-CC
Plant Mitchell Unit 4 Combined Cycle
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 10
activities
in EN Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EN-CV-100
Civil Site Plan & Grading Design
03-Mar-25
02-May-25
10.0d
100%
EN-ME-200
Steam Turbine Foundation Spec
16-Mar-25
25-Apr-25
10.0d
100%
EN-EL-300
Substation Single Line Diagram
23-Mar-25
12-May-25
10.0d
100%
EN-CV-110
Foundation Design Package
31-Mar-25
19-Jun-25
10.0d
100%
EN-IC-400
P&IDs Issue for Construction
06-Apr-25
05-Jul-25
10.0d
100%
EN-ME-210
HRSG Mechanical Design
13-Apr-25
12-Jul-25
10.0d
100%
EN-ME-230
Piping Isometrics — U/G
27-Apr-25
26-Jun-25
10.0d
100%
EN-EL-310
Cable Schedule & Routing
04-May-25
23-Jul-25
10.0d
100%
EN-ME-220
Piping Isometrics — A/G
11-May-25
29-Aug-25
10.0d
100%
EN-IC-410
Control System Architecture
18-May-25
27-Jul-25
10.0d
100%