PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 4 activities in CN.EL.SW Substation & Switchgear × clear
Code
Activity
Start
Finish
Flt
%
CN-EL-SW-1400
Switchyard Foundation
15-Feb-26
27-Mar-26
10.0d
100%
CN-EL-SW-1410
Substation Equipment Setting
05-Apr-26
25-May-26
10.0d
37%
CN-EL-SW-1430
Transformer Setting
31-May-26
30-Jun-26
10.0d
0%
CN-EL-SW-1420
MV Switchgear Install
30-Aug-26
29-Oct-26
0.0d
0%
Q1 2026 Q2 2026 Q3 2026 Q4 2026 Data Date
CN-EL-SW-1400 — Switchyard Foundation | 15-Feb-26 → 27-Mar-26 | Complete 100% | float 10.0d CN-EL-SW-1400 CN-EL-SW-1410 — Substation Equipment Setting | 05-Apr-26 → 25-May-26 | In Progress 37% | float 10.0d CN-EL-SW-1410 CN-EL-SW-1430 — Transformer Setting | 31-May-26 → 30-Jun-26 | Not Started 0% | float 10.0d CN-EL-SW-1420 — MV Switchgear Install | 30-Aug-26 → 29-Oct-26 | Not Started 0% | float 0.0d CN-EL-SW-1420