PMU4-CC
Plant Mitchell Unit 4 Combined Cycle
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 4
activities
in CN.EL.SW Substation & Switchgear
× clear
Code
Activity
Start
Finish
Flt
%
CN-EL-SW-1400
Switchyard Foundation
15-Feb-26
27-Mar-26
10.0d
100%
CN-EL-SW-1410
Substation Equipment Setting
05-Apr-26
25-May-26
10.0d
37%
CN-EL-SW-1430
Transformer Setting
31-May-26
30-Jun-26
10.0d
0%
CN-EL-SW-1420
MV Switchgear Install
30-Aug-26
29-Oct-26
0.0d
0%