Projects
PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 5 activities in CN.EL.AG Above Ground Electrical × clear
Code
Activity
Start
Finish
Flt
%
CN-EL-AG-1300
Cable Tray Install
12-Jul-26
20-Sep-26
0.0d
0%
CN-EL-AG-1310
Cable Pulling — A/G
20-Sep-26
19-Dec-26
0.0d
0%
CN-EL-AG-1320
Lighting Install
04-Oct-26
03-Dec-26
5.0d
0%
CN-EL-AG-1330
Motor Connections
08-Nov-26
28-Dec-26
0.0d
0%
CN-EL-AG-1340
Heat Tracing
13-Dec-26
12-Jan-27
10.0d
0%
29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec 04-Jan 11-Jan 18-Jan 25-Jan Data Date
CN-EL-AG-1300 — Cable Tray Install | 12-Jul-26 → 20-Sep-26 | Not Started 0% | float 0.0d CN-EL-AG-1300 CN-EL-AG-1310 — Cable Pulling — A/G | 20-Sep-26 → 19-Dec-26 | Not Started 0% | float 0.0d CN-EL-AG-1310 CN-EL-AG-1320 — Lighting Install | 04-Oct-26 → 03-Dec-26 | Not Started 0% | float 5.0d CN-EL-AG-1320 CN-EL-AG-1330 — Motor Connections | 08-Nov-26 → 28-Dec-26 | Not Started 0% | float 0.0d CN-EL-AG-1330 CN-EL-AG-1340 — Heat Tracing | 13-Dec-26 → 12-Jan-27 | Not Started 0% | float 10.0d CN-EL-AG-1340