Projects
PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 4 activities in CN.EL.UG Underground Electrical × clear
Code
Activity
Start
Finish
Flt
%
CN-EL-UG-1220
Grounding Grid Install
24-Aug-25
23-Sep-25
10.0d
100%
CN-EL-UG-1200
U/G Conduit Bank Install
21-Sep-25
20-Nov-25
10.0d
100%
CN-EL-UG-1230
Manholes & Pull Boxes
02-Nov-25
27-Nov-25
15.0d
100%
CN-EL-UG-1210
U/G Cable Pulling
30-Nov-25
09-Jan-26
10.0d
100%
Aug 2025 Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Data Date
CN-EL-UG-1220 — Grounding Grid Install | 24-Aug-25 → 23-Sep-25 | Complete 100% | float 10.0d CN-EL-UG-1220 CN-EL-UG-1200 — U/G Conduit Bank Install | 21-Sep-25 → 20-Nov-25 | Complete 100% | float 10.0d CN-EL-UG-1200 CN-EL-UG-1230 — Manholes & Pull Boxes | 02-Nov-25 → 27-Nov-25 | Complete 100% | float 15.0d CN-EL-UG-1230 CN-EL-UG-1210 — U/G Cable Pulling | 30-Nov-25 → 09-Jan-26 | Complete 100% | float 10.0d CN-EL-UG-1210