PMU4-CC
Plant Mitchell Unit 4 Combined Cycle
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 13
activities
in CN.EL Electrical
× clear
Code
Activity
Start
Finish
Flt
%
CN-EL-UG-1220
Grounding Grid Install
24-Aug-25
23-Sep-25
10.0d
100%
CN-EL-UG-1200
U/G Conduit Bank Install
21-Sep-25
20-Nov-25
10.0d
100%
CN-EL-UG-1230
Manholes & Pull Boxes
02-Nov-25
27-Nov-25
15.0d
100%
CN-EL-UG-1210
U/G Cable Pulling
30-Nov-25
09-Jan-26
10.0d
100%
CN-EL-SW-1400
Switchyard Foundation
15-Feb-26
27-Mar-26
10.0d
100%
CN-EL-SW-1410
Substation Equipment Setting
05-Apr-26
25-May-26
10.0d
37%
CN-EL-SW-1430
Transformer Setting
31-May-26
30-Jun-26
10.0d
0%
CN-EL-AG-1300
Cable Tray Install
12-Jul-26
20-Sep-26
0.0d
0%
CN-EL-SW-1420
MV Switchgear Install
30-Aug-26
29-Oct-26
0.0d
0%
CN-EL-AG-1310
Cable Pulling — A/G
20-Sep-26
19-Dec-26
0.0d
0%
CN-EL-AG-1320
Lighting Install
04-Oct-26
03-Dec-26
5.0d
0%
CN-EL-AG-1330
Motor Connections
08-Nov-26
28-Dec-26
0.0d
0%
CN-EL-AG-1340
Heat Tracing
13-Dec-26
12-Jan-27
10.0d
0%