PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 13 activities in CN.EL Electrical × clear
Code
Activity
Start
Finish
Flt
%
CN-EL-UG-1220
Grounding Grid Install
24-Aug-25
23-Sep-25
10.0d
100%
CN-EL-UG-1200
U/G Conduit Bank Install
21-Sep-25
20-Nov-25
10.0d
100%
CN-EL-UG-1230
Manholes & Pull Boxes
02-Nov-25
27-Nov-25
15.0d
100%
CN-EL-UG-1210
U/G Cable Pulling
30-Nov-25
09-Jan-26
10.0d
100%
CN-EL-SW-1400
Switchyard Foundation
15-Feb-26
27-Mar-26
10.0d
100%
CN-EL-SW-1410
Substation Equipment Setting
05-Apr-26
25-May-26
10.0d
37%
CN-EL-SW-1430
Transformer Setting
31-May-26
30-Jun-26
10.0d
0%
CN-EL-AG-1300
Cable Tray Install
12-Jul-26
20-Sep-26
0.0d
0%
CN-EL-SW-1420
MV Switchgear Install
30-Aug-26
29-Oct-26
0.0d
0%
CN-EL-AG-1310
Cable Pulling — A/G
20-Sep-26
19-Dec-26
0.0d
0%
CN-EL-AG-1320
Lighting Install
04-Oct-26
03-Dec-26
5.0d
0%
CN-EL-AG-1330
Motor Connections
08-Nov-26
28-Dec-26
0.0d
0%
CN-EL-AG-1340
Heat Tracing
13-Dec-26
12-Jan-27
10.0d
0%
Aug 2025 Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Jan 2027 Data Date
CN-EL-UG-1220 — Grounding Grid Install | 24-Aug-25 → 23-Sep-25 | Complete 100% | float 10.0d CN-EL-UG-1220 CN-EL-UG-1200 — U/G Conduit Bank Install | 21-Sep-25 → 20-Nov-25 | Complete 100% | float 10.0d CN-EL-UG-1200 CN-EL-UG-1230 — Manholes & Pull Boxes | 02-Nov-25 → 27-Nov-25 | Complete 100% | float 15.0d CN-EL-UG-1230 CN-EL-UG-1210 — U/G Cable Pulling | 30-Nov-25 → 09-Jan-26 | Complete 100% | float 10.0d CN-EL-UG-1210 CN-EL-SW-1400 — Switchyard Foundation | 15-Feb-26 → 27-Mar-26 | Complete 100% | float 10.0d CN-EL-SW-1400 CN-EL-SW-1410 — Substation Equipment Setting | 05-Apr-26 → 25-May-26 | In Progress 37% | float 10.0d CN-EL-SW-1410 CN-EL-SW-1430 — Transformer Setting | 31-May-26 → 30-Jun-26 | Not Started 0% | float 10.0d CN-EL-SW-1430 CN-EL-AG-1300 — Cable Tray Install | 12-Jul-26 → 20-Sep-26 | Not Started 0% | float 0.0d CN-EL-AG-1300 CN-EL-SW-1420 — MV Switchgear Install | 30-Aug-26 → 29-Oct-26 | Not Started 0% | float 0.0d CN-EL-SW-1420 CN-EL-AG-1310 — Cable Pulling — A/G | 20-Sep-26 → 19-Dec-26 | Not Started 0% | float 0.0d CN-EL-AG-1310 CN-EL-AG-1320 — Lighting Install | 04-Oct-26 → 03-Dec-26 | Not Started 0% | float 5.0d CN-EL-AG-1320 CN-EL-AG-1330 — Motor Connections | 08-Nov-26 → 28-Dec-26 | Not Started 0% | float 0.0d CN-EL-AG-1330 CN-EL-AG-1340 — Heat Tracing | 13-Dec-26 → 12-Jan-27 | Not Started 0% | float 10.0d CN-EL-AG-1340