PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 13 activities in CN.EL Electrical × clear
Code
Activity
Start
Finish
Flt
%
CN-EL-UG-1220
Grounding Grid Install
24-Aug-25
23-Sep-25
10.0d
100%
CN-EL-UG-1200
U/G Conduit Bank Install
21-Sep-25
20-Nov-25
10.0d
100%
CN-EL-UG-1230
Manholes & Pull Boxes
02-Nov-25
27-Nov-25
15.0d
100%
CN-EL-UG-1210
U/G Cable Pulling
30-Nov-25
09-Jan-26
10.0d
100%
CN-EL-SW-1400
Switchyard Foundation
15-Feb-26
27-Mar-26
10.0d
100%
CN-EL-SW-1410
Substation Equipment Setting
05-Apr-26
25-May-26
10.0d
37%
CN-EL-SW-1430
Transformer Setting
31-May-26
30-Jun-26
10.0d
0%
CN-EL-AG-1300
Cable Tray Install
12-Jul-26
20-Sep-26
0.0d
0%
CN-EL-SW-1420
MV Switchgear Install
30-Aug-26
29-Oct-26
0.0d
0%
CN-EL-AG-1310
Cable Pulling — A/G
20-Sep-26
19-Dec-26
0.0d
0%
CN-EL-AG-1320
Lighting Install
04-Oct-26
03-Dec-26
5.0d
0%
CN-EL-AG-1330
Motor Connections
08-Nov-26
28-Dec-26
0.0d
0%
CN-EL-AG-1340
Heat Tracing
13-Dec-26
12-Jan-27
10.0d
0%
28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan Data Date
CN-EL-UG-1220 — Grounding Grid Install | 24-Aug-25 → 23-Sep-25 | Complete 100% | float 10.0d CN-EL-UG-1220 CN-EL-UG-1200 — U/G Conduit Bank Install | 21-Sep-25 → 20-Nov-25 | Complete 100% | float 10.0d CN-EL-UG-1200 CN-EL-UG-1230 — Manholes & Pull Boxes | 02-Nov-25 → 27-Nov-25 | Complete 100% | float 15.0d CN-EL-UG-1230 CN-EL-UG-1210 — U/G Cable Pulling | 30-Nov-25 → 09-Jan-26 | Complete 100% | float 10.0d CN-EL-UG-1210 CN-EL-SW-1400 — Switchyard Foundation | 15-Feb-26 → 27-Mar-26 | Complete 100% | float 10.0d CN-EL-SW-1400 CN-EL-SW-1410 — Substation Equipment Setting | 05-Apr-26 → 25-May-26 | In Progress 37% | float 10.0d CN-EL-SW-1410 CN-EL-SW-1430 — Transformer Setting | 31-May-26 → 30-Jun-26 | Not Started 0% | float 10.0d CN-EL-SW-1430 CN-EL-AG-1300 — Cable Tray Install | 12-Jul-26 → 20-Sep-26 | Not Started 0% | float 0.0d CN-EL-AG-1300 CN-EL-SW-1420 — MV Switchgear Install | 30-Aug-26 → 29-Oct-26 | Not Started 0% | float 0.0d CN-EL-SW-1420 CN-EL-AG-1310 — Cable Pulling — A/G | 20-Sep-26 → 19-Dec-26 | Not Started 0% | float 0.0d CN-EL-AG-1310 CN-EL-AG-1320 — Lighting Install | 04-Oct-26 → 03-Dec-26 | Not Started 0% | float 5.0d CN-EL-AG-1320 CN-EL-AG-1330 — Motor Connections | 08-Nov-26 → 28-Dec-26 | Not Started 0% | float 0.0d CN-EL-AG-1330 CN-EL-AG-1340 — Heat Tracing | 13-Dec-26 → 12-Jan-27 | Not Started 0% | float 10.0d CN-EL-AG-1340