Projects
PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 8 activities in CN.PI Mechanical/Piping × clear
Code
Activity
Start
Finish
Flt
%
CN-PI-1100
Set Steam Turbine Generator
12-Jul-26
10-Sep-26
0.0d
0%
CN-PI-1110
Set HRSG Modules
26-Jul-26
24-Oct-26
0.0d
0%
CN-PI-1130
Cooling Water Piping
23-Aug-26
11-Nov-26
5.0d
0%
CN-PI-1140
BOP Equipment Setting
06-Sep-26
15-Nov-26
5.0d
0%
CN-PI-1120
Main Steam Piping Install
13-Sep-26
11-Jan-27
0.0d
0%
CN-PI-1150
Fuel Gas Piping
11-Oct-26
10-Dec-26
10.0d
0%
CN-PI-1170
Condensate Piping
08-Nov-26
18-Dec-26
10.0d
0%
CN-PI-1160
Auxiliary Steam Piping
15-Nov-26
04-Jan-27
5.0d
0%
Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Jan 2027 Data Date
CN-PI-1100 — Set Steam Turbine Generator | 12-Jul-26 → 10-Sep-26 | Not Started 0% | float 0.0d CN-PI-1100 CN-PI-1110 — Set HRSG Modules | 26-Jul-26 → 24-Oct-26 | Not Started 0% | float 0.0d CN-PI-1110 CN-PI-1130 — Cooling Water Piping | 23-Aug-26 → 11-Nov-26 | Not Started 0% | float 5.0d CN-PI-1130 CN-PI-1140 — BOP Equipment Setting | 06-Sep-26 → 15-Nov-26 | Not Started 0% | float 5.0d CN-PI-1140 CN-PI-1120 — Main Steam Piping Install | 13-Sep-26 → 11-Jan-27 | Not Started 0% | float 0.0d CN-PI-1120 CN-PI-1150 — Fuel Gas Piping | 11-Oct-26 → 10-Dec-26 | Not Started 0% | float 10.0d CN-PI-1150 CN-PI-1170 — Condensate Piping | 08-Nov-26 → 18-Dec-26 | Not Started 0% | float 10.0d CN-PI-1170 CN-PI-1160 — Auxiliary Steam Piping | 15-Nov-26 → 04-Jan-27 | Not Started 0% | float 5.0d CN-PI-1160