PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 5 activities in CN.ST Structural Steel × clear
Code
Activity
Start
Finish
Flt
%
CN-ST-1000
STG Building Steel Erection
04-Jan-26
25-Mar-26
0.0d
100%
CN-ST-1010
HRSG Steel Erection
15-Feb-26
26-May-26
0.0d
67%
CN-ST-1020
Plant Building Steel
29-Mar-26
28-May-26
10.0d
42%
CN-ST-1030
Stack Erection
10-May-26
19-Jun-26
5.0d
0%
CN-ST-1040
Crane Rails & Monorails
31-May-26
30-Jun-26
10.0d
0%
29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun Data Date
CN-ST-1000 — STG Building Steel Erection | 04-Jan-26 → 25-Mar-26 | Complete 100% | float 0.0d CN-ST-1000 CN-ST-1010 — HRSG Steel Erection | 15-Feb-26 → 26-May-26 | In Progress 67% | float 0.0d CN-ST-1010 CN-ST-1020 — Plant Building Steel | 29-Mar-26 → 28-May-26 | In Progress 42% | float 10.0d CN-ST-1020 CN-ST-1030 — Stack Erection | 10-May-26 → 19-Jun-26 | Not Started 0% | float 5.0d CN-ST-1030 CN-ST-1040 — Crane Rails & Monorails | 31-May-26 → 30-Jun-26 | Not Started 0% | float 10.0d CN-ST-1040