Projects
PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 5 activities in CN.ST Structural Steel × clear
Code
Activity
Start
Finish
Flt
%
CN-ST-1000
STG Building Steel Erection
04-Jan-26
25-Mar-26
0.0d
100%
CN-ST-1010
HRSG Steel Erection
15-Feb-26
26-May-26
0.0d
67%
CN-ST-1020
Plant Building Steel
29-Mar-26
28-May-26
10.0d
42%
CN-ST-1030
Stack Erection
10-May-26
19-Jun-26
5.0d
0%
CN-ST-1040
Crane Rails & Monorails
31-May-26
30-Jun-26
10.0d
0%
29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun Data Date
CN-ST-1000 — STG Building Steel Erection | 04-Jan-26 → 25-Mar-26 | Complete 100% | float 0.0d CN-ST-1000 CN-ST-1010 — HRSG Steel Erection | 15-Feb-26 → 26-May-26 | In Progress 67% | float 0.0d CN-ST-1010 CN-ST-1020 — Plant Building Steel | 29-Mar-26 → 28-May-26 | In Progress 42% | float 10.0d CN-ST-1020 CN-ST-1030 — Stack Erection | 10-May-26 → 19-Jun-26 | Not Started 0% | float 5.0d CN-ST-1030 CN-ST-1040 — Crane Rails & Monorails | 31-May-26 → 30-Jun-26 | Not Started 0% | float 10.0d CN-ST-1040