Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 6 activities in CN.CV Civil/Foundations × clear
Code
Activity
Start
Finish
Flt
%
CN-CV-900
STG Foundation Excavation
27-Jul-25
05-Sep-25
0.0d
100%
CN-CV-910
STG Foundation Rebar & Forms
14-Sep-25
13-Nov-25
0.0d
100%
CN-CV-930
HRSG Foundation Construction
05-Oct-25
03-Jan-26
0.0d
100%
CN-CV-920
STG Foundation Pour & Cure
16-Nov-25
16-Dec-25
0.0d
100%
CN-CV-940
BOP Equipment Foundations
07-Dec-25
27-Mar-26
5.0d
100%
CN-CV-950
Switchyard Foundations
18-Jan-26
19-Mar-26
10.0d
100%
Q3 2025 Q4 2025 Q1 2026 Data Date
CN-CV-900 — STG Foundation Excavation | 27-Jul-25 → 05-Sep-25 | Complete 100% | float 0.0d CN-CV-900 CN-CV-910 — STG Foundation Rebar & Forms | 14-Sep-25 → 13-Nov-25 | Complete 100% | float 0.0d CN-CV-910 CN-CV-930 — HRSG Foundation Construction | 05-Oct-25 → 03-Jan-26 | Complete 100% | float 0.0d CN-CV-930 CN-CV-920 — STG Foundation Pour & Cure | 16-Nov-25 → 16-Dec-25 | Complete 100% | float 0.0d CN-CV-940 — BOP Equipment Foundations | 07-Dec-25 → 27-Mar-26 | Complete 100% | float 5.0d CN-CV-940 CN-CV-950 — Switchyard Foundations | 18-Jan-26 → 19-Mar-26 | Complete 100% | float 10.0d CN-CV-950