PMU4-CC
Plant Mitchell Unit 4 Combined Cycle
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 6
activities
in CN.CV Civil/Foundations
× clear
Code
Activity
Start
Finish
Flt
%
CN-CV-900
STG Foundation Excavation
27-Jul-25
05-Sep-25
0.0d
100%
CN-CV-910
STG Foundation Rebar & Forms
14-Sep-25
13-Nov-25
0.0d
100%
CN-CV-930
HRSG Foundation Construction
05-Oct-25
03-Jan-26
0.0d
100%
CN-CV-920
STG Foundation Pour & Cure
16-Nov-25
16-Dec-25
0.0d
100%
CN-CV-940
BOP Equipment Foundations
07-Dec-25
27-Mar-26
5.0d
100%
CN-CV-950
Switchyard Foundations
18-Jan-26
19-Mar-26
10.0d
100%