Projects
PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 5 activities in CN.SP Site Preparation × clear
Code
Activity
Start
Finish
Flt
%
CN-SP-800
Mobilize to Site
16-Mar-25
05-Apr-25
0.0d
100%
CN-SP-810
Site Clearing & Grubbing
06-Apr-25
06-May-25
0.0d
100%
CN-SP-820
Mass Excavation
04-May-25
13-Jun-25
0.0d
100%
CN-SP-830
Site Drainage Install
15-Jun-25
15-Jul-25
0.0d
100%
CN-SP-840
Construction Power
06-Jul-25
26-Jul-25
10.0d
100%
Mar 2025 Apr 2025 May 2025 Jun 2025 Jul 2025 Data Date
CN-SP-800 — Mobilize to Site | 16-Mar-25 → 05-Apr-25 | Complete 100% | float 0.0d CN-SP-800 CN-SP-810 — Site Clearing & Grubbing | 06-Apr-25 → 06-May-25 | Complete 100% | float 0.0d CN-SP-810 CN-SP-820 — Mass Excavation | 04-May-25 → 13-Jun-25 | Complete 100% | float 0.0d CN-SP-820 CN-SP-830 — Site Drainage Install | 15-Jun-25 → 15-Jul-25 | Complete 100% | float 0.0d CN-SP-830 CN-SP-840 — Construction Power | 06-Jul-25 → 26-Jul-25 | Complete 100% | float 10.0d CN-SP-840