PMU4-CC
Plant Mitchell Unit 4 Combined Cycle
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 44
activities
in CN Construction
× clear
Code
Activity
Start
Finish
Flt
%
CN-SP-800
Mobilize to Site
16-Mar-25
05-Apr-25
0.0d
100%
CN-SP-810
Site Clearing & Grubbing
06-Apr-25
06-May-25
0.0d
100%
CN-SP-820
Mass Excavation
04-May-25
13-Jun-25
0.0d
100%
CN-SP-830
Site Drainage Install
15-Jun-25
15-Jul-25
0.0d
100%
CN-SP-840
Construction Power
06-Jul-25
26-Jul-25
10.0d
100%
CN-CV-900
STG Foundation Excavation
27-Jul-25
05-Sep-25
0.0d
100%
CN-EL-UG-1220
Grounding Grid Install
24-Aug-25
23-Sep-25
10.0d
100%
CN-CV-910
STG Foundation Rebar & Forms
14-Sep-25
13-Nov-25
0.0d
100%
CN-EL-UG-1200
U/G Conduit Bank Install
21-Sep-25
20-Nov-25
10.0d
100%
CN-CV-930
HRSG Foundation Construction
05-Oct-25
03-Jan-26
0.0d
100%
CN-EL-UG-1230
Manholes & Pull Boxes
02-Nov-25
27-Nov-25
15.0d
100%
CN-CV-920
STG Foundation Pour & Cure
16-Nov-25
16-Dec-25
0.0d
100%
CN-EL-UG-1210
U/G Cable Pulling
30-Nov-25
09-Jan-26
10.0d
100%
CN-CV-940
BOP Equipment Foundations
07-Dec-25
27-Mar-26
5.0d
100%
CN-ST-1000
STG Building Steel Erection
04-Jan-26
25-Mar-26
0.0d
100%
CN-CV-950
Switchyard Foundations
18-Jan-26
19-Mar-26
10.0d
100%
CN-ST-1010
HRSG Steel Erection
15-Feb-26
26-May-26
0.0d
67%
CN-EL-SW-1400
Switchyard Foundation
15-Feb-26
27-Mar-26
10.0d
100%
CN-ST-1020
Plant Building Steel
29-Mar-26
28-May-26
10.0d
42%
CN-EL-SW-1410
Substation Equipment Setting
05-Apr-26
25-May-26
10.0d
37%
CN-ST-1030
Stack Erection
10-May-26
19-Jun-26
5.0d
0%
CN-EL-SW-1430
Transformer Setting
31-May-26
30-Jun-26
10.0d
0%
CN-ST-1040
Crane Rails & Monorails
31-May-26
30-Jun-26
10.0d
0%
CN-EL-AG-1300
Cable Tray Install
12-Jul-26
20-Sep-26
0.0d
0%
CN-PI-1100
Set Steam Turbine Generator
12-Jul-26
10-Sep-26
0.0d
0%
CN-PI-1110
Set HRSG Modules
26-Jul-26
24-Oct-26
0.0d
0%
CN-PI-1130
Cooling Water Piping
23-Aug-26
11-Nov-26
5.0d
0%
CN-EL-SW-1420
MV Switchgear Install
30-Aug-26
29-Oct-26
0.0d
0%
CN-PI-1140
BOP Equipment Setting
06-Sep-26
15-Nov-26
5.0d
0%
CN-PI-1120
Main Steam Piping Install
13-Sep-26
11-Jan-27
0.0d
0%
CN-EL-AG-1310
Cable Pulling — A/G
20-Sep-26
19-Dec-26
0.0d
0%
CN-IC-1520
DCS Cabinet Install
20-Sep-26
30-Oct-26
5.0d
0%
CN-EL-AG-1320
Lighting Install
04-Oct-26
03-Dec-26
5.0d
0%
CN-IC-1500
Field Instrument Install
11-Oct-26
30-Dec-26
0.0d
0%
CN-PI-1150
Fuel Gas Piping
11-Oct-26
10-Dec-26
10.0d
0%
CN-EL-AG-1330
Motor Connections
08-Nov-26
28-Dec-26
0.0d
0%
CN-PI-1170
Condensate Piping
08-Nov-26
18-Dec-26
10.0d
0%
CN-IC-1510
Instrument Tubing
15-Nov-26
04-Jan-27
5.0d
0%
CN-PI-1160
Auxiliary Steam Piping
15-Nov-26
04-Jan-27
5.0d
0%
CN-PN-1620
Tank Insulation
15-Nov-26
15-Dec-26
15.0d
0%
CN-PN-1600
Pipe Insulation
22-Nov-26
21-Jan-27
5.0d
0%
CN-PN-1610
Equipment Painting
06-Dec-26
15-Jan-27
10.0d
0%
CN-EL-AG-1340
Heat Tracing
13-Dec-26
12-Jan-27
10.0d
0%
CN-IC-1530
Loop Checks
03-Jan-27
04-Mar-27
0.0d
0%