PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 44 activities in CN Construction × clear
Code
Activity
Start
Finish
Flt
%
CN-SP-800
Mobilize to Site
16-Mar-25
05-Apr-25
0.0d
100%
CN-SP-810
Site Clearing & Grubbing
06-Apr-25
06-May-25
0.0d
100%
CN-SP-820
Mass Excavation
04-May-25
13-Jun-25
0.0d
100%
CN-SP-830
Site Drainage Install
15-Jun-25
15-Jul-25
0.0d
100%
CN-SP-840
Construction Power
06-Jul-25
26-Jul-25
10.0d
100%
CN-CV-900
STG Foundation Excavation
27-Jul-25
05-Sep-25
0.0d
100%
CN-EL-UG-1220
Grounding Grid Install
24-Aug-25
23-Sep-25
10.0d
100%
CN-CV-910
STG Foundation Rebar & Forms
14-Sep-25
13-Nov-25
0.0d
100%
CN-EL-UG-1200
U/G Conduit Bank Install
21-Sep-25
20-Nov-25
10.0d
100%
CN-CV-930
HRSG Foundation Construction
05-Oct-25
03-Jan-26
0.0d
100%
CN-EL-UG-1230
Manholes & Pull Boxes
02-Nov-25
27-Nov-25
15.0d
100%
CN-CV-920
STG Foundation Pour & Cure
16-Nov-25
16-Dec-25
0.0d
100%
CN-EL-UG-1210
U/G Cable Pulling
30-Nov-25
09-Jan-26
10.0d
100%
CN-CV-940
BOP Equipment Foundations
07-Dec-25
27-Mar-26
5.0d
100%
CN-ST-1000
STG Building Steel Erection
04-Jan-26
25-Mar-26
0.0d
100%
CN-CV-950
Switchyard Foundations
18-Jan-26
19-Mar-26
10.0d
100%
CN-ST-1010
HRSG Steel Erection
15-Feb-26
26-May-26
0.0d
67%
CN-EL-SW-1400
Switchyard Foundation
15-Feb-26
27-Mar-26
10.0d
100%
CN-ST-1020
Plant Building Steel
29-Mar-26
28-May-26
10.0d
42%
CN-EL-SW-1410
Substation Equipment Setting
05-Apr-26
25-May-26
10.0d
37%
CN-ST-1030
Stack Erection
10-May-26
19-Jun-26
5.0d
0%
CN-EL-SW-1430
Transformer Setting
31-May-26
30-Jun-26
10.0d
0%
CN-ST-1040
Crane Rails & Monorails
31-May-26
30-Jun-26
10.0d
0%
CN-EL-AG-1300
Cable Tray Install
12-Jul-26
20-Sep-26
0.0d
0%
CN-PI-1100
Set Steam Turbine Generator
12-Jul-26
10-Sep-26
0.0d
0%
CN-PI-1110
Set HRSG Modules
26-Jul-26
24-Oct-26
0.0d
0%
CN-PI-1130
Cooling Water Piping
23-Aug-26
11-Nov-26
5.0d
0%
CN-EL-SW-1420
MV Switchgear Install
30-Aug-26
29-Oct-26
0.0d
0%
CN-PI-1140
BOP Equipment Setting
06-Sep-26
15-Nov-26
5.0d
0%
CN-PI-1120
Main Steam Piping Install
13-Sep-26
11-Jan-27
0.0d
0%
CN-EL-AG-1310
Cable Pulling — A/G
20-Sep-26
19-Dec-26
0.0d
0%
CN-IC-1520
DCS Cabinet Install
20-Sep-26
30-Oct-26
5.0d
0%
CN-EL-AG-1320
Lighting Install
04-Oct-26
03-Dec-26
5.0d
0%
CN-IC-1500
Field Instrument Install
11-Oct-26
30-Dec-26
0.0d
0%
CN-PI-1150
Fuel Gas Piping
11-Oct-26
10-Dec-26
10.0d
0%
CN-EL-AG-1330
Motor Connections
08-Nov-26
28-Dec-26
0.0d
0%
CN-PI-1170
Condensate Piping
08-Nov-26
18-Dec-26
10.0d
0%
CN-IC-1510
Instrument Tubing
15-Nov-26
04-Jan-27
5.0d
0%
CN-PI-1160
Auxiliary Steam Piping
15-Nov-26
04-Jan-27
5.0d
0%
CN-PN-1620
Tank Insulation
15-Nov-26
15-Dec-26
15.0d
0%
CN-PN-1600
Pipe Insulation
22-Nov-26
21-Jan-27
5.0d
0%
CN-PN-1610
Equipment Painting
06-Dec-26
15-Jan-27
10.0d
0%
CN-EL-AG-1340
Heat Tracing
13-Dec-26
12-Jan-27
10.0d
0%
CN-IC-1530
Loop Checks
03-Jan-27
04-Mar-27
0.0d
0%
Mar 2025 Apr 2025 May 2025 Jun 2025 Jul 2025 Aug 2025 Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Jan 2027 Feb 2027 Mar 2027 Data Date
CN-SP-800 — Mobilize to Site | 16-Mar-25 → 05-Apr-25 | Complete 100% | float 0.0d CN-SP-800 CN-SP-810 — Site Clearing & Grubbing | 06-Apr-25 → 06-May-25 | Complete 100% | float 0.0d CN-SP-810 CN-SP-820 — Mass Excavation | 04-May-25 → 13-Jun-25 | Complete 100% | float 0.0d CN-SP-820 CN-SP-830 — Site Drainage Install | 15-Jun-25 → 15-Jul-25 | Complete 100% | float 0.0d CN-SP-830 CN-SP-840 — Construction Power | 06-Jul-25 → 26-Jul-25 | Complete 100% | float 10.0d CN-SP-840 CN-CV-900 — STG Foundation Excavation | 27-Jul-25 → 05-Sep-25 | Complete 100% | float 0.0d CN-CV-900 CN-EL-UG-1220 — Grounding Grid Install | 24-Aug-25 → 23-Sep-25 | Complete 100% | float 10.0d CN-EL-UG-1220 CN-CV-910 — STG Foundation Rebar & Forms | 14-Sep-25 → 13-Nov-25 | Complete 100% | float 0.0d CN-CV-910 CN-EL-UG-1200 — U/G Conduit Bank Install | 21-Sep-25 → 20-Nov-25 | Complete 100% | float 10.0d CN-EL-UG-1200 CN-CV-930 — HRSG Foundation Construction | 05-Oct-25 → 03-Jan-26 | Complete 100% | float 0.0d CN-CV-930 CN-EL-UG-1230 — Manholes & Pull Boxes | 02-Nov-25 → 27-Nov-25 | Complete 100% | float 15.0d CN-EL-UG-1230 CN-CV-920 — STG Foundation Pour & Cure | 16-Nov-25 → 16-Dec-25 | Complete 100% | float 0.0d CN-CV-920 CN-EL-UG-1210 — U/G Cable Pulling | 30-Nov-25 → 09-Jan-26 | Complete 100% | float 10.0d CN-EL-UG-1210 CN-CV-940 — BOP Equipment Foundations | 07-Dec-25 → 27-Mar-26 | Complete 100% | float 5.0d CN-CV-940 CN-ST-1000 — STG Building Steel Erection | 04-Jan-26 → 25-Mar-26 | Complete 100% | float 0.0d CN-ST-1000 CN-CV-950 — Switchyard Foundations | 18-Jan-26 → 19-Mar-26 | Complete 100% | float 10.0d CN-CV-950 CN-ST-1010 — HRSG Steel Erection | 15-Feb-26 → 26-May-26 | In Progress 67% | float 0.0d CN-ST-1010 CN-EL-SW-1400 — Switchyard Foundation | 15-Feb-26 → 27-Mar-26 | Complete 100% | float 10.0d CN-EL-SW-1400 CN-ST-1020 — Plant Building Steel | 29-Mar-26 → 28-May-26 | In Progress 42% | float 10.0d CN-ST-1020 CN-EL-SW-1410 — Substation Equipment Setting | 05-Apr-26 → 25-May-26 | In Progress 37% | float 10.0d CN-EL-SW-1410 CN-ST-1030 — Stack Erection | 10-May-26 → 19-Jun-26 | Not Started 0% | float 5.0d CN-ST-1030 CN-EL-SW-1430 — Transformer Setting | 31-May-26 → 30-Jun-26 | Not Started 0% | float 10.0d CN-EL-SW-1430 CN-ST-1040 — Crane Rails & Monorails | 31-May-26 → 30-Jun-26 | Not Started 0% | float 10.0d CN-ST-1040 CN-EL-AG-1300 — Cable Tray Install | 12-Jul-26 → 20-Sep-26 | Not Started 0% | float 0.0d CN-EL-AG-1300 CN-PI-1100 — Set Steam Turbine Generator | 12-Jul-26 → 10-Sep-26 | Not Started 0% | float 0.0d CN-PI-1100 CN-PI-1110 — Set HRSG Modules | 26-Jul-26 → 24-Oct-26 | Not Started 0% | float 0.0d CN-PI-1110 CN-PI-1130 — Cooling Water Piping | 23-Aug-26 → 11-Nov-26 | Not Started 0% | float 5.0d CN-PI-1130 CN-EL-SW-1420 — MV Switchgear Install | 30-Aug-26 → 29-Oct-26 | Not Started 0% | float 0.0d CN-EL-SW-1420 CN-PI-1140 — BOP Equipment Setting | 06-Sep-26 → 15-Nov-26 | Not Started 0% | float 5.0d CN-PI-1140 CN-PI-1120 — Main Steam Piping Install | 13-Sep-26 → 11-Jan-27 | Not Started 0% | float 0.0d CN-PI-1120 CN-EL-AG-1310 — Cable Pulling — A/G | 20-Sep-26 → 19-Dec-26 | Not Started 0% | float 0.0d CN-EL-AG-1310 CN-IC-1520 — DCS Cabinet Install | 20-Sep-26 → 30-Oct-26 | Not Started 0% | float 5.0d CN-IC-1520 CN-EL-AG-1320 — Lighting Install | 04-Oct-26 → 03-Dec-26 | Not Started 0% | float 5.0d CN-EL-AG-1320 CN-IC-1500 — Field Instrument Install | 11-Oct-26 → 30-Dec-26 | Not Started 0% | float 0.0d CN-IC-1500 CN-PI-1150 — Fuel Gas Piping | 11-Oct-26 → 10-Dec-26 | Not Started 0% | float 10.0d CN-PI-1150 CN-EL-AG-1330 — Motor Connections | 08-Nov-26 → 28-Dec-26 | Not Started 0% | float 0.0d CN-EL-AG-1330 CN-PI-1170 — Condensate Piping | 08-Nov-26 → 18-Dec-26 | Not Started 0% | float 10.0d CN-PI-1170 CN-IC-1510 — Instrument Tubing | 15-Nov-26 → 04-Jan-27 | Not Started 0% | float 5.0d CN-IC-1510 CN-PI-1160 — Auxiliary Steam Piping | 15-Nov-26 → 04-Jan-27 | Not Started 0% | float 5.0d CN-PI-1160 CN-PN-1620 — Tank Insulation | 15-Nov-26 → 15-Dec-26 | Not Started 0% | float 15.0d CN-PN-1620 CN-PN-1600 — Pipe Insulation | 22-Nov-26 → 21-Jan-27 | Not Started 0% | float 5.0d CN-PN-1600 CN-PN-1610 — Equipment Painting | 06-Dec-26 → 15-Jan-27 | Not Started 0% | float 10.0d CN-PN-1610 CN-EL-AG-1340 — Heat Tracing | 13-Dec-26 → 12-Jan-27 | Not Started 0% | float 10.0d CN-EL-AG-1340 CN-IC-1530 — Loop Checks | 03-Jan-27 → 04-Mar-27 | Not Started 0% | float 0.0d CN-IC-1530