PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 2 activities in PR.EB Electrical Bulks × clear
Code
Activity
Start
Finish
Flt
%
PR-EB-710
Procure Switchgear
10-Aug-25
07-Jan-26
0.0d
100%
PR-EB-700
Procure Cable & Conduit
14-Sep-25
13-Dec-25
5.0d
100%
28-Jul 04-Aug 11-Aug 18-Aug 25-Aug 01-Sep 08-Sep 15-Sep 22-Sep 29-Sep 06-Oct 13-Oct 20-Oct 27-Oct 03-Nov 10-Nov 17-Nov 24-Nov 01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan Data Date
PR-EB-710 — Procure Switchgear | 10-Aug-25 → 07-Jan-26 | Complete 100% | float 0.0d PR-EB-710 PR-EB-700 — Procure Cable & Conduit | 14-Sep-25 → 13-Dec-25 | Complete 100% | float 5.0d PR-EB-700